top of page
Concrete Porch- Tare Out & Replace
Mr. & Mrs. Forgey really needed to raise their porch as it was sinking and had already been lowered by almost 2". So 2, really tough days, for this tare out and set up in order to pour. Unfortunately the truck schedule wasn't on our side with the time frame allocated for this job and it was decided to hand pour with 80lb bags (never a recommended idea). So 237 bags and 9.5 hrs later we had dumped the last wheel barrel of concrete! Another 4 hours later the last few of us were finally able to head home. Sometimes you just have to do what it takes, despite the situation, and push through to delivery a great product!!









bottom of page